2020 Workcycle Sprint 7

Closed Apr 13, 2020 66% complete

Google Books:

  • complete devops docs - IN PROGRESS
    -- nagios monitoring: disk on GB and SDR API
    -- SLA levels
  • Update symphony with current status on the symphony side - IN PROGRESS
  • Enable technicalMetadata service in production - DONE
  • Enable Google Books in production - DONE
  • Bug fixes discovered after deployment - IN PROGRESS
  • Make Google Books repo private…

Google Books:

  • complete devops docs - IN PROGRESS
    -- nagios monitoring: disk on GB and SDR API
    -- SLA levels
  • Update symphony with current status on the symphony side - IN PROGRESS
  • Enable technicalMetadata service in production - DONE
  • Enable Google Books in production - DONE
  • Bug fixes discovered after deployment - IN PROGRESS
  • Make Google Books repo private - DONE

SDR Evolution:

  • Continued expanding number of cases covered by infra-integration testing - IN PROGRESS
  • Continued ETD update analysis and planning - DONE
  • Work with Goobi to enable use of new dor-services-app endpoint for re-accessioning - DONE
  • Testing the migration to the new data model - IN PROGRESS
    -- Run all existing objects through the cocina mapper to see where the gaps are
    -- Set up a design meeting (Andrew + all devs, optional) to answer questions:
    -- How to run the migration?
    -- How to chunk up/sequence the data (by object/content type, by collection, by APO, by druid alpha, by registration date, by tag)?
    -- Noting that web archives, ETDs, GIS, and other objects are different than others
    -- How can we do this work without taxing current systems?
    -- How to find/identify problematic gaps?
    -- Missing source IDs for some objects
    -- Do we store the mapped data for further analysis?

Preservation Migration:

  • Complete existing known object remediation - IN PROGRESS
    • 2 remaining
  • Dry-run of the first migration weekend (NOTE: deferred until April 3) - IN PROGRESS
  • investigate/planning for upcoming workcycle - IN PROGRESS

SDR Maintenance:

  • high priority bug fixes - IN PROGRESS