1: the answer is known and requires simply document the answer in detail to count as 'solved'.
2: a solid day of work to get the solution fully thought out and written down.
3: anywhere from 2 to 4 days of dedicated research time to arrive at a solution to the problems
4: a solid week (possibly more) is needed to arrive at a solution. In person sync time with other researchers may be required for E4.
5: at least a week of research time is needed, very likely more, and that very little progress can be made without face to face discussion with others.
This is the master plan for getting
Specs
into version 1Using this issue to track work that needs to be done in order for the 'spec' to be complete.
Refine & Review Specs
New Specs
Documentation
This plan uses the following issue as a template: https://github.com/filecoin-project/research/issues/26
Legend
(@whyrusleeping)