Motorola ArcPro Migration #446

Open
1 of 2 tasks
mhchou opened this issue Jun 5, 2024 · 8 comments
Open
1 of 2 tasks

Motorola ArcPro Migration #446

mhchou opened this issue Jun 5, 2024 · 8 comments
Assignees
Labels
carry forward This task was carried forward into the next quarter paying This issue earns $$ status: in progress This issue or pull request is being worked on

Comments

@mhchou
Copy link

mhchou commented Jun 5, 2024

Benefit

With ArcMap being retired from Esri, Motorola is retiring its system support to ArcMap and pushing every agency to upgrade to ArcPro.
With my involvement, I can

Acceptance Criteria

  • Shadow Motorola on the first 2 projects
  • Complete the upgrades within Motorola and the agencies' schedule

Notes

The tentative list of agencies that will be involved with the Pro upgrade projects is shown below:

ArcGIS Pro Migration (in order)
A full ArcGIS Pro Migration would be needed. The first two agencies we would go through as part of a traditional 5 week process. The remaining efforts could be streamlined to less time.

✅Logan PD, UT
✅Tooele County Sheriff, UT
✅Wasatch County Sheriff, UT
Layton PD, UT
(NEXT?) Weber 911, UT
Utah County Sheriff, UT
Washington County Sheriff, UT
Iron County ITS, UT
Kane County Sheriff, UT

GeoValidation Upgrade & ArcGIS Pro Migration
Motorola Solutions GIS Analyst would be more involved with these efforts to support the GeoValidaiton activation. The build of the ArcPro setup would be the same process as the above category.
*agencies that we are still confirming their current Address Validation platform (classic, sentryx, geovalidation)

Millard County Sheriff, UT
University of Utah PD, UT
Beaver County Sheriff, UT*
Emery County Sheriff, UT*
Summit County Sheriff, UT*
Sevier County Sheriff, UT*
Granite School District, UT*

Completed or Nearing Completion

✅Salt Lake Communications, UT
✅Price DPS Communications, UT
✅Uintah Basin, UT
➡️Box Elder County, UT
Grand County, UT

Risks

A lot of uncertainties in working with many entities within a short period. Motorola is having a major personnel reshuffle internally. The target schedule is aggressive which could lead to overpromising.

Issue Reference

refs #381

@mhchou mhchou changed the title ArcPro Upgrades Motorola ArcPro Migration Aug 20, 2024
@mhchou
Copy link
Author

mhchou commented Aug 20, 2024

Logan went live on 8/20

@gregbunce
Copy link

Tooele County Sheriff, UT migration will begin Sept 9th

@gregbunce
Copy link

@gregbunce - reach back out to Lynn regarding the contract.

@mhchou mhchou moved this to In Progress in UGRC PI Planning Objectives Sep 26, 2024
@mhchou mhchou added status: in progress This issue or pull request is being worked on paying This issue earns $$ labels Sep 26, 2024
@mhchou
Copy link
Author

mhchou commented Sep 26, 2024

Tooele data was built and went into practice on 9/23.

@gregbunce gregbunce added the carry forward This task was carried forward into the next quarter label Sep 26, 2024
@mhchou
Copy link
Author

mhchou commented Dec 9, 2024

Wasatch kicked off on 10/17.

@mhchou
Copy link
Author

mhchou commented Dec 9, 2024

Tooele went live on 10/16.

@mhchou
Copy link
Author

mhchou commented Dec 9, 2024

Wasatch went live on 12/9.

@mhchou
Copy link
Author

mhchou commented Dec 9, 2024

Working with Box Elder currently, trying to connect the FLEX server to the GIS server. After services have good connections, they will go into practice.

Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment
Labels
carry forward This task was carried forward into the next quarter paying This issue earns $$ status: in progress This issue or pull request is being worked on
Projects
Status: In Progress
Development

No branches or pull requests

2 participants