Table of Contents
- Review what tasks remain
- Review sprint statistics
BurnUp Chart
Velocity Chart
Control Chart
- To understand scope change, velocity shift and reasons why not starting some tasks
- Introduce, discuss and estimate the tasks
- Note uncertain things and assign someone responsible to clarify the requirements
- AGREE on the sprint goal(s) - no more than three
- Decide what should be done and what should not be done
We should NOT
start any development if there are no estimation in the tasks
Scale: Fibonacci number
is a good tool to follow
Assign the number of story points to a task by:
- the amount of understanding
- the effort to implement
- the testing effort on
developers
- 1 (very easy, can be done in less than 1 hour)
- 2 (easy, but need time to implement and verify, maybe need to spend 1 to several hours)
- 3 (medium, expected to spend around 1 day to finish it)
- 5 (complicated, expected days)
Break down the task if larger than 5
- 8 (very complicated, expected a week)
- 13 (it will be super huge that we cannot imagine, even cant estimate the timeline)
- spike
It is possible to say the task is a spike
, which means we do not know how to implement it
- Before the sprint starts:
- Only Bugs / Tasks tickets have story points
- Do not put tasks that exceeds the agreed capacity in any cases